CALAIS PORT 2015 : a complex project in terms of design and construction

Calais Port 2015 main technical challenge is the disparity of works to be executed and the nesting of these works together, both in features and phasing at the design stage and also regarding the construction schedule.

Dredging the basin protected by the breakwater is conditioned by the breakwater construction progress ; dredging allowing new platforms to be implemented with backfilling from dredging ; after burying multiple networks of fluids and energy, buildings will then be implemented on these platforms …