PROGRESS OF THE PROTECTION SEAWALL ON THE BREAKWATER

2019/09/02

This work progresses “backwards”, in other words it starts on a breakwater distant point to go back towards the land. And more precisely, 3 workshops are working simultaneously: section 3, section 2 and section 1.

Seawall Section 3 is 735 meters long and located between PM 1000 and PM 1770. It begins at the end of the platform and is therefore the first part of the basin protection.

The slab of this section is made, the first prefabricated parts were layed on to cover the reinforcement waiting to be filled with concrete. Ducts were placed inside in particular to bring electricity to the signal lights at the end of the breakwater.

This area includes 3 turning areas, so that the vehicles have the space to turn back. Some of these areas will accommodate marine signaling.