Bridge No.2 foundation works

7 engineering structures will be built for Calais Port 2015.

Bridge No.2 foundation works have already started. This structure will be made of coated beams and will have two spans, the first one over two roadways and the other one over railways. The site is first stripped and then prepared to implement embankments for bridge and roads. Bridge No.2 foundations are made with piles whose locations are drilled by auger then their metal frames lowered and foundations are at last filled up with concrete.